What the per-key figure actually contains
Read more
The first question is what is being divided. Some estimates include only guestroom FF&E. Others spread lobby, restaurant, meeting room and corridor costs across all keys, which raises the figure without changing a single guestroom. Some include carpet, wallcovering and installation labor; others carry those in a separate renovation budget. Operating supplies such as linens, towels and in-room amenities are OS&E and are usually budgeted separately, even when they are replaced in the same project.
Before comparing two numbers, write down the spaces included, the product categories included, what is being reused and what is excluded. A per-key figure without that scope sheet is not a budget. It also helps to note the year of the pricing, since a figure carried forward from an older project may not reflect current product and freight costs.
How a brand PIP sets the scope
Read more
For a branded hotel, the property improvement plan, or PIP, is the franchisor's list of required upgrades. A PIP is typically issued when a hotel changes ownership, converts to a new brand or renews its franchise agreement, and it often sets deadlines for completing the work. It may call for anything from new soft goods to a full guestroom and public area renovation built to the brand's current design package.
The owner's job is to turn the PIP into a priced item list. Walk the property against the PIP, record what can stay and what must go, and note items that trigger related work, such as a new headboard that moves the outlets or a new bathroom vanity light that needs a different junction box location. Keep required items separate from owner-elected upgrades so the budget shows what the brand requires and what the owner chose.
Soft goods, case goods and full renovation
Read more
Hotel teams usually describe renovation scope in tiers. A soft goods renovation replaces the softer, faster-wearing layer: carpet, wallcovering, drapery and sheers, bedspreads or duvet covers, upholstery and sometimes lamps and art. A case goods renovation replaces the hard furniture: headboards, nightstands, desks, dressers or wardrobes and media units. A full renovation does both, often with bathroom and lighting work.
Carpet and wallcovering are technically installed finishes, but hotels often carry them in the FF&E renovation budget, which is another reason two per-key figures can differ. A soft goods scope is narrower, but it is not automatically simple: rooms still have to be measured, emptied, worked and returned to inventory on a tight cycle.
The main drivers of cost per key
Read more
Once scope is fixed, a handful of variables move the number most.
- Brand tier and design standard: the specified level of finish and construction for casegoods and seating.
- Custom versus catalog product: custom pieces carry design, sampling and prototype costs that are spread across the quantity ordered.
- Room mix: kings, double queens, suites and accessible rooms each need different packages, so a property with many room types has more line items.
- Quantities and attic stock: spare carpet, wallcovering, fabric and some furniture bought with the original order to match dye lots for future repairs.
- Freight, warehousing and handling: product cost is only part of the path to the room.
- Installation labor and removal: taking out and disposing of old furniture is part of a replacement project and is easy to leave out.
- Schedule: a compressed schedule or a phased one changes storage, labor and crew costs.
Model rooms and the mock-up step
Read more
Many hotel renovations build a model room before releasing full production. The model room tests the furniture, finishes and lighting in a real guestroom so the owner, the brand and the operator can approve them, and it often surfaces fit problems that drawings missed: a desk that blocks a thermostat, a headboard that clears the outlet on one wall type but not another.
The model room has its own cost and its own time, and changes made after it can affect the full order. Building it into the estimate and schedule from the start protects the per-key figure from a late surprise.
Phasing around an operating hotel
Read more
Most replacement work happens while the hotel stays open. Rooms are taken out of inventory in blocks, often a floor or part of a floor at a time, worked and returned. That plan shapes cost: product may sit in storage longer, deliveries are split into many loads, installation crews return repeatedly and elevator time has to be shared with guests and housekeeping.
The operator and the owner should agree on how many rooms can be out of service at once before the estimate is final, because that one decision changes freight, storage and labor. If phasing changes later, the per-key figure built on the old plan will not hold.
Building and protecting the estimate
Read more
A defensible estimate is built from the bottom up: item list by room type, quantities from the room mix, product pricing by tier, then freight, warehousing, installation, removal, attic stock, tax where it applies and contingency. Divide by keys only at the end, and keep the scope sheet attached.
To protect it, approve the item list rather than renderings, lock quantities before purchase orders go out and review every substitution for size, durability, lead time and brand compliance as well as price. An alternate that looks cheaper can cost more if it fails the brand review or needs a second installation visit. Tracking each change against the scope sheet keeps the owner able to explain the number to a lender or asset manager.
Planning a hotel FF&E project
Read more
Level Up Interiors works on hospitality FF&E from selection through installation. The hotel FF&E service page explains how the firm approaches guestroom and public area packages.